Building Permit Resolution Services (Permit Amendments)
The Permit Amendments group assists property owners and contractors in resolving open and expired building permits. We also work closely with title and real estate companies, and prospective buyers to address permit issues that arise through the sale of a structure utilizing our property search services.
Effective 01/16/2024 - Extension, Cancellation, Change of Contractor, Change of Sub-Contractor, Contractor Withdrawal, Sub-Contractor Withdrawal requests will need to be uploaded to the ‘Request Changes to Contractor or Permit Status’ condition in the portal. These requests will no longer be processed through email.
Extensions
Effect of Governor's Emergency Orders on Existing Permits
What Effect Does the Governor's Emergency Orders have on Existing Permits?
Executive Order 22-218, issued September 23, 2022, qualifies as a “natural emergency” pursuant to Florida law, which allows for the tolling of certain permits for the duration of the emergency declaration and for up to six months in addition to the tolled period (see s.252.363, F.S.).
This applies to the following:
- The expiration of a development order issued by a local government
- The expiration of a building permit
- The expiration of a permit issued by the Florida Department of Environmental Protection or a water management district pursuant to part IV of Chapter 373, F.S.
- The buildout date of a development of regional impact, including any extension of a buildout date that previously granted as specified in s.380.06(7)(c), F.S.
Extensions
An extension is a request submitted to reactivate and/or extend the life of a building application or building permit.
Extensions are for permits that have been issued and are nearing/or have reached their expiration date.
Request Change to Contractor Status(PDF, 9MB)
Building Application Extension Process
Building Application Extension Process
Allow up to 2 business days from the initial date extension is requested.
- Licensed contractor/owner-builder or design professional submits an extension request.
- BPRS group reviews request.
- Applicable fees will need to be paid at time of permit issuance.
Is your building application in an expired status?
Prior to your application being expired was it in reject status?
- Submit a building application extension form and once it is approved you will have an additional 90 days to submit corrections. This also applies to revisions that have outstanding correction comments that didn’t get addressed within the 180 day timeframe.
Prior to your application being expired was it is a ready for issuance status?
- Submit a building application extension form and once it is approved you will have an additional 90 days to get your permit issued.
- If you submitted in person you will need to pick up your building permit, if it was submitted on the portal you will receive an email once the permit has been issued.
Building Permit Extension
General Permit Extension Process
Allow up to 7 business days from the initial date extension is requested.
- Licensed contractor/owner-builder submits extension request.
- BPRS reviews request.
- If extension fee is applied, fee is required to be paid prior to pursuing pending permit-related items.
- Licensed contractor/owner-builder addresses pending permit-related items.
Extending an Older Permit (1959-October 2011)
What should I expect when extending an older permit?
- BPRS will provide you a new permit and inspection job card, after your extension request is approved.
- Prior to scheduling a pending inspection(s), make sure you have your permit, inspection job card and job site copy of plans on the job site visible for our inspectors.
What should I expect when extending an older permit application?
- You cannot extend an older permit application. A new permit application is required to be submitted.
Once I extended my older permit, do the same extension rules apply when extending a current permit?
Extending a Current Permit (October 2011-Present)
Who can submit an extension request?
- Individual who has signed the qualifiers page within permit application.
Can the property owner submit an extension request?
- No. Although the property owner owns the property, individual who submitted a permit application owns the permit application/permit.
How much time is added to my permit?
How much time is added if I submit an extension request before my permit expires?
- 90 calendar days from the current expiration date.
How much time is added if I submit an extension request after my permit has expired?
- 90 calendar days from the date BPRS processes extension.
How much does an extension request cost?
- Minimum $100.00, but not to exceed $500.00.
How many times can I submit an extension request?
- Three attempts. Additional request must be approved by the Building Official.
Can I extend my permit if it is in a VOID status?
- No, You will need to submit a new permit application.
Frequently Asked Questions
Building Permit Extension
Is your permit in an issued status?
- You will need to have an inspection result in pass/partial pass/pass with notes within 180 calendar days from the date permit application was issued.
Do I get additional time if my inspection results in a pass/partial pass/pass with notes?
- Yes. An additional 180 calendar days is added to the current expiration date from the last passed inspection.
What if I pass multiple inspections on the same day?
- 180 calendar days are added from the last passed inspection.
- Example. You pass your 115 and 502 inspections on January 1st, 2019. Permit expiration date extends 180 calendar days from January 1st, 2019. You do not get 180 calendar days for each passed inspection if passed on the same day.
Is your permit in an inspection commenced status?
- Yes. You will need to schedule and pass any remaining inspections and address other permit-related items.
Is your permit in an inspection completed status?
- All your fees are paid.
- Conditions are resolved.
- All inspections have passed.
- If there are no additional permit-related items, email our inspections section at Inspections@collier.gov and request a certificate of completion/occupancy.
What will not extend the life of my permit?
- Receiving a fail as an inspection result.
- Paying an outstanding balance.
- Submitting any required documents: survey, compaction test, elevation certificate, etc.
- Scheduling an inspection.
- Submitting a revision.
Cancellations
Cancellation Process
General Cancellation Process
Allow for up to 5 business days for BPRS to review your request. If you are submitting a cancellation request for a Fire permit then the process may take longer. These requests have to be reviewed and approved by the Fire District and may require inspections performed by the Fire District.
Request Changes to Contractor or Permit Status, Refer to the instructions for Scenario 2: Cancellation of Permit
Frequently Asked Questions
How much does it cost to cancel my permit application/permit?
- There is no cancellation fee. Only pending applicable fee(s) are required to be paid prior to scheduling a cancellation inspection.
How do I find out if I have any pending applicable fees?
- Visit our GMD Public Portal.
- BPRS will provide a payment slip after a cancellation request is submitted.
What are applicable fees?
- Any fee generated from services rendered by Growth Management Department.
Who is authorized to sign a cancellation form?
- Individual who signed the qualifiers page within the permit application.
Where do I submit a cancellation request?
- Upload to the "Request Changes to Contractor or Permit Status"condition on the GMD Public Portal.
What if I want to cancel my revision?
- Upload to the "Request Changes to Contractor or Permit Status"condition on the GMD Public Portal.
Can I cancel a permit if I am the property owner?
- No. If the permit was applied for by a licensed contractor. The licensed contractor will need to submit a cancellation request.
- Yes. If it is an owner-builder permit.
What are my options to cancel a permit if I am the property owner?
- If the contractor you hired is still active, you will need to send a termination letter (refer to last page of change of contractor form).
- Provide the BPRS section a copy of termination letter and certified mail receipt, along with a cancellation form.
If I submit new permit application, will an older permit with a similar if not same scope get cancelled?
- No. BPRS does not approve a cancellation based on the scope of work, but what is indicated in the plans.
What does it mean if my cancellation request is denied?
- Incorrect individual signed the cancellation form.
- Inspector verified work has commenced.
- BPRS has concluded a newer permit does not supersede an older permit.
What do I do if I am a licensed contractor, work has commenced, and I am terminated by the home owner?
- The contractor may request to be removed from the permit by submitting a completed Contractor Withdrawal
What do I do if I submitted a permit application with the wrong address?
- You will need to submit a new permit application with correct address.
- Submitting a revision to change the address will not be accepted.
When is the best time to submit a cancellation request?
- As soon as possible. BPRS will look to see what services have been rendered prior to submission of cancellation date.
Change of Contractor
Change of Contractor
Request Changes to Contractor or Permit Status Form
A Change of Contractor process occurs when there is a change as to who will be responsible for a building application/permit.
Building Permit Resolution Services (BPRS) processes change of contractors for active and expired building permits.
Change of Contractor for an Active or Expired Permit
Upload to the "Request Changes to Contractor or Permit Status" condition on the Public Portal.
Frequently Asked Questions
Is there a fee charged when changing a contractor?
Do I have to submit a change of contractor if there is only a change in qualifier?
Contractor Withdrawal
Contractor Withdrawal Process
(PDF, 9MB)Click to Download(PDF, 9MB) Form(PDF, 9MB)
Contractor Withdrawal is a process undergone by a licensed contractor who no longer wants to be associated with a building application/permit.
General Contractor Withdrawal Procedure
- Contractor uploads the "Request Changes to Contractor or Permit Status" form to the condition on the Public Portal.
- BPRS reviews request.
- If request is approved, BPRS will provide contractor withdrawal process.
- If request is denied, BPRS will instruct contractor how best to proceed.
- Contractor submits all required letters.
- BPRS performs a final review and process request.
Frequently Asked Questions
Are there fees associated with the contractor withdrawal procedure?
- Only applicable fees are required to be paid prior to a contractor being withdrawn.
How many times do I have to send the ‘Letter of Notification’?
- A minimum of two attempts.
When can I start to send my second attempt?
- Allow a minimum of 1 calendar week from the date of your first attempt.
What if the property owner has more than one address?
- You will need to send the ‘Letter of Notification’ to all addresses, with a minimum of two attempts.
- Example –
- 123 Main Street, Naples, FL 34104.
- Schorbachstrasse 9, 35510 Butzbach, Germany
What if I received a signed certified mail receipt?
- Provide a signed copy to the BPRS section to avoid the need for a second attempt.
What if USPS tracking says it was "Delivered"?
- A second attempt is required?
What if USPS tracking says it was "Refused"?
- A second attempt is required.
Expired Notifications
What Should I Do If I Receive an Expired Application Notice
A Expired Application Notice is a letter generated by the Building Permit Outtake group, notifying a licensed contractor/owner builder that their permit has expired.
What should I do if I received an expired application notice?
- Be aware of the date indicated on notice (see highlighted area in image above). If you do not submit an extension/cancellation form prior to date indicated on letter, your permit will be set to a VOID status.
What are my options now that my permit status is VOID?
- Submit a cancellation request if the work has/will not commence.
- Submit a new permit application.
What does a VOID status mean?
- You can no longer address any permit-related items, except for paying outstanding applicable fees.
What happens if there are outstanding applicable fees on my permit?
- If you are a licensed contractor, your license will be placed on hold until the balance is paid.
How do I remove a hold related to fees from my license?
- Pay the outstanding balance.
- Notify the BPRS section once the balance has been paid. Payment must be posted to permit, prior to license being taken off hold.
- To check the status of your payment, contact our cashiering department at 239-252-5119.
What if I still want to pursue the scope of work associated with my VOID permit?
- You will need to submit a new permit application?
What if I passed my rough inspections, and my permit has been set to VOID?
- You will need to submit a new permit application.
What if my permit was in a previous code cycle and now we are in a new code cycle?
- Plans will need to be brought up to current code cycle.
What if I passed some inspections, my permit was in a previous code cycle and now we are in a new code cycle?
- Plans will need to be brought up to current code cycle.
- Inspections passed within a previous code cycle will be grandfathered into your new permit application.
What about money I paid on my now VOID permit?
- If you choose to pursue the scope of work, we will transfer certain fees to your new permit application.
- If you choose not to pursue the scope of work, we may refund certain fees, if a refund for the fees is applicable.
- Refer to section ‘FF’ of our fee schedule(PDF, 14MB) for refund process.
Will my new permit application supersede my VOID permit?
- Plans will need to be compared to determine if new permit application truly supersedes a VOID permit.
- Writing “Reapplication of permit #” on a new permit application does not guarantee an automatic cancellation of a VOID permit.
What if I didn’t receive an expired permit notice and my permit was still set to VOID?
- BPRS will send an expired permit notice to email indicated on permit application.
- For a licensed contractor, if no email is provided, the notice will be sent via USPS to address(es) indicated on the DBPR website.
- For an owner-builder, if no email is provided, the notice will be sent via USPS to address(es) indicated on the Property Appraiser’s website.
What Should I Do If I Receive an Expired Permit Notice
What should I do if I received an expired permit notice?
- Be aware of the date indicated on notice (see highlighted area in image above). If you do not submit an extension/cancellation form prior to date indicated on letter, your permit will be set to a VOID status.
What are my options now that my permit status is VOID?
- Submit a cancellation request if the work has/will not commence.
- Submit a new permit application.
What does a VOID status mean?
- You can no longer address any permit-related items, except for paying outstanding applicable fees.
What happens if there are outstanding applicable fees on my permit?
- If you are a licensed contractor, your license will be placed on hold until the balance is paid.
How do I remove a hold related to fees from my license?
- Pay the outstanding balance.
- Notify the BPRS section once the balance has been paid. Payment must be posted to permit, prior to license being taken off hold.
- To check the status of your payment, contact our cashiering department at 239-252-5119.
What if I still want to pursue the scope of work associated with my VOID permit?
- You will need to submit a new permit application?
What if I passed my rough inspections, and my permit has been set to VOID?
- You will need to submit a new permit application.
What if my permit was in a previous code cycle and now we are in a new code cycle?
- Plans will need to be brought up to current code cycle.
What if I passed some inspections, my permit was in a previous code cycle and now we are in a new code cycle?
- Plans will need to be brought up to current code cycle.
- Inspections passed within a previous code cycle will be grandfathered into your new permit application.
What about money I paid on my now VOID permit?
- If you choose to pursue the scope of work, we will transfer certain fees to your new permit application.
- If you choose not to pursue the scope of work, we may refund certain fees, if a refund for the fees is applicable.
- Refer to section ‘FF’ of our fee schedule for refund process.
Will my new permit application supersede my VOID permit?
- Plans will need to be compared to determine if new permit application truly supersedes a VOID permit.
- Writing “Reapplication of permit #” on a new permit application does not guarantee an automatic cancellation of a VOID permit.
What if I didn’t receive an expired permit notice and my permit was still set to VOID?
- BPRS will send an expired permit notice to email indicated on permit application.
- For a licensed contractor, if no email is provided, the notice will be sent via USPS to address(es) indicated on the DBPR website.
- For an owner-builder, if no email is provided, the notice will be sent via USPS to address(es) indicated on the Property Appraiser’s website.